PROJECT—Education

Joseph Kerr Middle School
Phase 4

Details

Client: Elk Grove Unified School District

Size: 18,705 sq. ft.

Completion: August 2026

Delivery Method: Lease-Leaseback

Location: Elk Grove, CA

Service: Facility Assessment, Master Planning, Needs Assessment, Planning, Site Planning, Architectural Design, Interior Design, Construction Documents, Construction Administration

Team

Principal-in-Charge: Brian Maytum

Senior Project Coordinator: Alex Balais

General Contractor: F&H Construction

Electrical Engineer: Edge Electrical Consulting

Civil Engineer: Warren Consulting Engineers

Mechanical Engineer: Weston & Associates Mechanical Engineers

Structural Engineer: Degenkolb

Low Voltage: KMM Services

Landscape Architecture: MTW Group

PROJECT DESCRIPTION

The project builds upon previous campus planning efforts and provides a clear direction for continued improvements at Joseph Kerr Middle School. Earlier phases included a new gymnasium and science center, significant site infrastructure improvements, demolition of the existing gymnasium, and upgrades to classrooms and the library in Buildings B, C, and D. Completed in August 2021, these improvements established the foundation for continued campus revitalization.
As part of the overall campus master plan developed by Nacht & Lewis, this phase replaced three aging buildings and eight relocatable classrooms with new, purpose-built construction. Designed to integrate with the modernized campus and create a new eastern entrance, the building includes general classrooms for the math department, a modern maker space focused on design and wood fabrication, an art studio, computer lab, recording studio, and special education spaces for students with disabilities. A centralized workroom with office and conference space supports teacher collaboration and student and parent engagement. Shaded outdoor areas provide secure spaces for outdoor learning and student use during lunch and breaks.
The site and building design followed the framework established in Nacht & Lewis’ master plan, replacing aging facilities with flexible, contemporary learning environments that support student safety and evolving educational needs. Key challenges included extensive demolition of cast-concrete buildings, undocumented utilities, and hazardous materials while maintaining full campus operations. Careful project phasing was critical to maintaining a safe, functional campus throughout construction. The building design prioritized flexible, adaptable spaces rather than program-specific uses, while outdoor areas extended learning opportunities beyond the classroom.

Contact us about this project!

Objective

Replace aging campus buildings with new, flexible facilities that support contemporary learning environments, enhance student safety, and align with the vision established in Nacht & Lewis’ master plan.

Challenge

Extensive demolition of cast-concrete buildings, undocumented utilities, and hazardous materials, while maintaining a safe and fully operational campus throughout construction.

Solution

Implement careful Phase 4 project phasing to maintain campus operations and student safety, while designing flexible, adaptable learning spaces and incorporating outdoor areas that extend learning beyond the classroom.

VIEW SIMILAR PROJECTS